Construction Update 07-21-2018

July 21st, 2018 by

Interior drywall work continues as exterior is prepared for upcoming installation of final finishes. Several drone shots showing the overall level of completion of the exterior. Drywall finishing underway to prepare for paint and other finishes. Porcelain tile installation has started in the service bay area. Exterior insulation and girt installation continues to prepare for…

Posted in New Facility

Construction Update 07-14-2018

July 14th, 2018 by

Drywall is being hung on the interior marking the transition into the finishes stage of the project! Drywall is being hung on the walls and ceilings of the first floor and service drive. Exterior insulation has been installed over all of the block walls allowing metal panels to be installed in the coming week. Tile…

Posted in New Facility

Construction Update 06-30-2018

June 30th, 2018 by

Still pushing on the interior to reach the milestone of hanging drywall while the exterior is being prepped to receive metal panels. Exterior waterproofing is complete and installation of the SMARTci continuous insulation system is in progress. Once this insulation is installed over the block walls, the corrugated metal panels will be installed. Framing of…

Posted in New Facility

Construction Update 06-23-2018

June 23rd, 2018 by
Construction-Update

Getting closer to having the building dried in with the installation of the skylight, additional exterior waterproofing, and some temporary enclosures, which will allow drywall activities to begin. The framework for the skylight was installed last week and glass will be finalized this week. Waterproofing coating has been applied to the exterior sheathing. Exterior insulation…

Posted in New Facility

Construction Update 06-09-2018

June 9th, 2018 by
Construction-Update

A heavy focus on “drying in” the exterior of the building with roofing, sheathing, and waterproofing activities will make way interior finishes to begin in the near future. The above drone photo shows the latest progress of the building with the Stono River in the backdrop. The above photo captured a Charleston sunset from the…

Posted in New Facility

Construction Update 06-02-2018

June 2nd, 2018 by
Construction-Update-Roof

Interior walls are framed with the focus shifting to overhead ceiling framing. Mechanical, electrical, plumbing, and sprinkler rough-ins continue to make steady progress. Laser scanning was performed to obtain precise measurements for the exterior perforated metal panels. The scanner details the exterior framework so the panels can be fabricated for an exact fit. White markers…

Posted in New Facility

Construction Update 05-26-2018

May 26th, 2018 by
New-Facility-Update

Hope everyone had a nice Memorial Day Weekend! Last week, interior framing took place allowing electrical and plumbing wall rough-ins to push forward. The shop structure was completed, opening up that space for interior work to begin. Drone images from early last week show the exterior building shell progressing with exterior framing and parapet walls…

Posted in New Facility

Construction Update 05/19/2018

May 19th, 2018 by
Construction-Update-May

The exterior framing has been installed across the front of the building while mechanical, electrical, and plumbing rough-ins continue, and block work nears completion. The exterior framing really showcases the unique curved facade that wraps around the entire front elevation of this building. With the framing complete for the roof parapet walls, the roof system…

Posted in New Facility

Construction Update 05/12/2018

May 12th, 2018 by
0512-Update-4

The structure of the building is really taking shape with the majority of the steel and roof decking installed on the front elevation. The roof joist installation at the showroom was completed, followed by roof decking installation. A safety stand down event was held onsite to reinforce the importance of site safety with a focus…

Posted in New Facility

Construction Update 05/05/2018

May 7th, 2018 by
0505-Update1

The steel and block structure continue to push along, HVAC ductwork installation is progressing, and roofing should begin in a few weeks. Structural steel installation continues with the front half of the building nearing completion. Masonry block work was completed for the service drive area and continues at the upstairs parts area and the shop….

Posted in New Facility
Saved
Saved Vehicles ×

SAVED VEHICLES

You don't have any saved vehicles!

Look for this link on your favorites:

Save

Once you've saved some vehicles, you can view them here at any time.

Contact
Contact Us ×

(843) 996-1452

Call Now

1511 Savannah Highway • Charleston, SC 29407

Get Directions

Today's Hours:

Open Today! Sales: 9am-7pm

Open Today! Service: 7:30am-6pm

Open Today! Parts: 7:30am-6pm

Porsche Charleston

1511 Savannah Highway Charleston, SC

Phone: (843) 996-1452

http://maps.google.com/?q=1511%20Savannah%20Highway%2C%20Charleston%2C%20SC%2029407

Parts

Phone: (843) 996-1454

1511 Savannah Highway Charleston, SC

Sales

Phone: (843) 996-1452

1511 Savannah Highway Charleston, SC

Service

Phone: (843) 996-1453

1511 Savannah Highway Charleston, SC

Collision Center

Phone: (910) 338-3853

1511 Savannah Highway Charleston, SC
32.7845519 -80.004105
[schema type="organization" orgtype="LocalBusiness" url="www.porschecharleston.com" name="Porsche Charleston" description="" street="1511 Savannah Highway" city="Charleston" state="SC" postalcode="29407" country="US" email="jmarino@bakermotorcompany.com; service@bakermotorcompany.com" phone="(843) 996-1452" logo="https://di-uploads-pod15.dealerinspire.com/porschecharleston/uploads/2018/06/Baker_All_Stores-15_1080x720.jpg"]
Porsche Charleston
Porsche Charleston
1511 Savannah Highway
Charleston, SC, 29407 US
(843) 996-1452
https://di-uploads-pod15.dealerinspire.com/porschecharleston/uploads/2018/06/Baker_All_Stores-15_1080x720.jpg
Porsche Charleston 32.7845519, -80.004105.