Now Open: The All-New Porsche Charleston

December 19th, 2018 by

Our team is thrilled to debut the all-new Porsche Charleston! With 20,000 square feet of pure Porsche, it’s more than a dealership, it’s an experience unlike any other.  Our brand new, stand-alone Porsche facility on Savannah Highway features the full range of Porsche models in an environment that truly celebrates this iconic brand. Every detail in this…

Porsche Charleston Construction Update 10/13/2018

October 17th, 2018 by

The vision continues to become a reality with Porsche Charleston’s construction progress. The final pieces are starting to come together. The tile is now complete in the service bay area, carpet has been installed, and final painting is nearing completion. Take a look at the latest progress below!  The service bay area received a lot of…

Posted in New Facility

Porsche Charleston Construction Update 10-9-18

October 9th, 2018 by

Porsche Charleston’s construction continues to make great progress! The interior and exterior have continued to come together making the vision become reality. Glass walls along with permanent overhead lighting have been installed, and the interior columns have been painted with a specialty finish. The exterior of the building structure is almost completely finished and the metal…

Posted in New Facility

Porsche Charleston Construction Update 9-22-18

September 27th, 2018 by

Construction continues on the brand new Porsche Charleston! Work has progressed throughout the interior of the building. Underground utilities have been connected, marking a huge milestone for the project. Fine grading, curbing, and exterior work is set to ramp up during the upcoming weeks. Construction crews spent late nights breaking up a portion of Highway 17 to…

Posted in New Facility

Construction Update 07-21-2018

July 21st, 2018 by

Interior drywall work continues as exterior is prepared for upcoming installation of final finishes. Several drone shots showing the overall level of completion of the exterior. Drywall finishing underway to prepare for paint and other finishes. Porcelain tile installation has started in the service bay area. Exterior insulation and girt installation continues to prepare for…

Posted in New Facility

Construction Update 07-14-2018

July 14th, 2018 by

Drywall is being hung on the interior marking the transition into the finishes stage of the project! Drywall is being hung on the walls and ceilings of the first floor and service drive. Exterior insulation has been installed over all of the block walls allowing metal panels to be installed in the coming week. Tile…

Posted in New Facility

Construction Update 06-30-2018

June 30th, 2018 by

Still pushing on the interior to reach the milestone of hanging drywall while the exterior is being prepped to receive metal panels. Exterior waterproofing is complete and installation of the SMARTci continuous insulation system is in progress. Once this insulation is installed over the block walls, the corrugated metal panels will be installed. Framing of…

Posted in New Facility

Construction Update 06-23-2018

June 23rd, 2018 by
Construction-Update

Getting closer to having the building dried in with the installation of the skylight, additional exterior waterproofing, and some temporary enclosures, which will allow drywall activities to begin. The framework for the skylight was installed last week and glass will be finalized this week. Waterproofing coating has been applied to the exterior sheathing. Exterior insulation…

Posted in New Facility

Construction Update 06-09-2018

June 9th, 2018 by
Construction-Update

A heavy focus on “drying in” the exterior of the building with roofing, sheathing, and waterproofing activities will make way interior finishes to begin in the near future. The above drone photo shows the latest progress of the building with the Stono River in the backdrop. The above photo captured a Charleston sunset from the…

Posted in New Facility

Construction Update 06-02-2018

June 2nd, 2018 by
Construction-Update-Roof

Interior walls are framed with the focus shifting to overhead ceiling framing. Mechanical, electrical, plumbing, and sprinkler rough-ins continue to make steady progress. Laser scanning was performed to obtain precise measurements for the exterior perforated metal panels. The scanner details the exterior framework so the panels can be fabricated for an exact fit. White markers…

Posted in New Facility