Construction Update 04/07/2018

April 7th, 2018 by

Structural steel erection began this week while the mason’s continued to make progress on the block walls.


0407-Update
Overview of the current progress of the structure shows masonry continuing to increase in height with structural steel making good progress as well.
0407-Update2
Steel beams have been set in the load bearing masonry beam pockets.

0407-Update3
Steel decking installation began and will continue to installed allowing the second floor concrete deck to be poured.
0407-Update4
Masons continued setting blocks working to stay ahead of the structural steel installation progress.
0407-Update5
Scaffolding is staged and ready for the masons to avoid any delays when moving from area to area.

Upcoming Week Look Ahead:

  • Masonry block walls
  • In-wall plumbing and electrical rough-ins
  • Structural steel erection
Posted in New Facility