Construction Update 04/21/2018

April 21st, 2018 by

The second-floor slab was prepped, inspected, and poured this week. Block and structural steel continue to make progress on the building structure while mechanical, electrical, and plumbing work to get a jump start on overhead rough-ins.


0421-Update1
Drone photo shows the progress of the block work, structural steel, and recent 2nd floor slab pour.
0421-Update2
Welders installed Nelson Studs to the steel decking, electrical conduits and floor outlets have been roughed-in.
0421-Update3
Welded wire mesh was placed on the 2nd floor readying it for concrete placement.

0421-Update4
0421-Update5

3 am concrete pour for the second-floor deck allowed the concrete trucks to travel to the site without encountering Charleston traffic. A pump truck was used to place the concrete on the upper deck and then powered trowels provided the finish.


0421-Update6
Overhead electrical conduits and mechanical ductwork hangers began to be installed under the second floor deck.
0421-Update7
Masonry block continues to make slow but steady progress. With the second floor deck poured, the masons will jump on the new slab and continue to take the block to final bearing height.
0421-Update8
Structural steel continues to be erected and the curved front facade is starting to take shape.

Upcoming Week Look Ahead:

  • Masonry block walls
  • Structural steel erection
  • Mechanical, electrical, and plumbing rough-ins
Posted in New Facility