Construction Update 05/05/2018

May 7th, 2018 by

The steel and block structure continue to push along, HVAC ductwork installation is progressing, and roofing should begin in a few weeks.


0505-Update2
Structural steel installation continues with the front half of the building nearing completion.
0505-Update3
Masonry block work was completed for the service drive area and continues at the upstairs parts area and the shop.
0505-Update4
HVAC ductwork installation progressed overhead precisely following the 3D coordination model to ensure everything fits as planned.

0505-Update5
Steel is almost ready for the roof decking to be installed on the front portion of the building.
0505-Update1
The exposed steel that will remain on the exterior of the building shell is galvanized for added protection against the elements over time.

Upcoming Week Look Ahead:

  • Masonry block walls
  • Structural steel erection
Posted in New Facility