Porsche Charleston Construction Update 10/13/2018

October 17th, 2018 by

The vision continues to become a reality with Porsche Charleston’s construction progress. The final pieces are starting to come together. The tile is now complete in the service bay area, carpet has been installed, and final painting is nearing completion. Take a look at the latest progress below! 

The service bay area received a lot of attention with tiling finishing throughout and shop lifts, toolboxes, and hose reels beginning the installation.

Carpet has been installed in the offices and conference room, allowing furniture installation to proceed this week. 

The storefront and exterior of the building are waiting on a few final pieces. We are excited to finalize the exterior in the oncoming weeks!

Upcoming Week Look Ahead:

  • Shop Equipment Installation
  • HVAC Test and Balance
  • Electrical and plumbing final inspections
  • Exterior metal panels
  • Curbing and final grading
  • Owner equipment and furniture move-in
Posted in New Facility