Porsche Charleston Construction Update 10-9-18
Porsche Charleston’s construction continues to make great progress! The interior and exterior have continued to come together making the vision become reality. Glass walls along with permanent overhead lighting have been installed, and the interior columns have been painted with a specialty finish. The exterior of the building structure is almost completely finished and the metal siding and garage bay doors have been installed.
Metal panels are being installed at the front curved elevation bringing the structure into its final form.
Glass walls and permanent overhead lighting have been installed, and the interior columns have been painted with a specialty finish.
Overhead painting is complete in the service bay and floor tile is completed in half of the area. Tile will continue in the remainder of the service area while shop lift installation begins in the completed section.
Sinks, countertops, and stainless steel partition walls have been installed in the bathrooms.
Upcoming Week Look Ahead:
· Office and showroom final paint
· Service Bay Tile
· Shop Equipment Installation
· HVAC startup
· HVAC Test and Balance
· Bathroom accessories installation